APPLICATION
The mixture’s reduced pot life should be taken into account – it is necessary to organise the application without pauses.
1. Paint
Once components A and B are mixed, apply directly to the primed substrate using a rubber squeegee, completing the application with a medium nap roller to remove blemishes. The second layer should be applied as soon as the first is sufficiently cured (1.5- 2.5 hours at 25ºC and 35% R.H). Apply at least 2 coats.
2. Multi-Layer
Apply a finishing coat of ADG Polyaspartic Topcoat,
using a rubber squeegee and short nap roller, to seal
the surface and encapsulate the aggregate. Do not
allow more than 18 hours to elapse between coats;
otherwise, sanding will be required.
COVERAGE
ADG PU Primer:
Approximately 7 m2/kg
ADG PU Basecoat:
Approximately 1 kg/m2/mm
ADG Polyaspartic Topcoat:
Approximately 10 m2/L to achieve 100µm
PACKAGING
ADG PU Primer: 20 kg pail
ADG PU Basecoat: 17.3 kg set
ADG Polyaspartic Topcoat: 40 L kits