Application
Surface Preparation
All surfaces must be clean and sound and free from all surface laitance, oil and grease. All defective concrete should be removed till sound concrete is detected.
Saw cut the repair locations to a depth of at least 10 mm to provide a square edge and to avoid feather-edging. Break out the complete repair area to a minimum depth of 10 mm up to the sawn edge.
Expose fully any corroded steel in the repair area and remove all loose scale and corrosion deposits by using hand held grinding tools. Steel should be free from contaminants and any foreign matters that may inhibit adhesion.
The substrate should be dampened with water or primed with QUICSEAL bonding agent or adhesive slurry.
Coverage / Yield
Consistency |
Required Volume of water |
Yield / bag |
Flowable |
4.3 – 4.5 litres |
13.5 litres |
Semi-Precast (Trowellable) |
3.3 – 3.5 litres |
12.0 litres |
Packaging
Pack size : 25kg bags